[EventId:202502081630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 February 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 8 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 February 2025.
Refer to market notice: 124362
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 8 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502081440_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 February 2025 14:40
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 8 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1440 hrs on 8 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502081340_review] Prices for interval 08-Feb-2025 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502081335_review] Prices for interval 08-Feb-2025 13:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502081330_review] Prices for interval 08-Feb-2025 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502081325_review] Prices for interval 08-Feb-2025 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502081320_review] Prices for interval 08-Feb-2025 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502081315_review] Prices for interval 08-Feb-2025 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations