Market Notices

124062RESERVE NOTICE04/02/2025 09:04:57 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124061 is cancelled at 0800 hrs 04/02/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
124061RESERVE NOTICE04/02/2025 07:52:40 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1500 hrs 05/02/2025.
The forecast capacity reserve requirement is 976 MW.
The minimum capacity reserve available is 908 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124060INTER-REGIONAL TRANSFER04/02/2025 05:11:43 AM

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.

The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124056MARKET INTERVENTION04/02/2025 04:08:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 05/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
124052RESERVE NOTICE03/02/2025 05:19:25 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124042 is cancelled at 1715 hrs 03/02/2025.

Manager NEM Real Time Operations
     
124044POWER SYSTEM EVENTS03/02/2025 02:13:15 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124043

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
124042RESERVE NOTICE03/02/2025 01:56:10 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

Manager NEM Real Time Operations
     
124041NON-CONFORMANCE03/02/2025 10:46:30 AM

NON-CONFORMANCE Region NSW1 Monday, 3 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 3 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     