Market Notices

122588MINIMUM SYSTEM LOAD30/12/2024 02:56:17 PM

Forecast Minimum System Load MSL1 condition in the VIC region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 122490 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
MSL1 - 1560 MW
MSL2 - 1060 MW
MSL3 - 560 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1264 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.


AEMO Operations
     
122584MARKET INTERVENTION30/12/2024 05:00:35 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122451


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1700 hrs 30/12/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 31/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 31/12/2024.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122583MARKET INTERVENTION30/12/2024 03:51:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122554

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 01/01/2025.

The direction update is issued at 1600 hrs 30/12/2024.

Manager NEM Real Time Operations
     
122582MARKET INTERVENTION30/12/2024 05:21:05 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122555

Direction is cancelled from: 1730 hrs 30/12/2024

Manager NEM Real Time Operations
     
122557MARKET INTERVENTION29/12/2024 06:16:38 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122546

Direction is cancelled from: 1800 hrs 29/12/2024

Manager NEM Real Time Operations
     
122555MARKET INTERVENTION29/12/2024 02:28:01 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122451


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1430 hrs 29/12/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 30/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1730 hrs 30/12/2024.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122554MARKET INTERVENTION29/12/2024 02:29:14 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122547

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 31/12/2024.

The direction update is issued at 1430 hrs 29/12/2024.

Manager NEM Real Time Operations
     
122553NON-CONFORMANCE29/12/2024 08:45:26 AM

NON-CONFORMANCE Region NSW1 Sunday, 29 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 28 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WLWLSF1
Duration: 28/12/2024 11:40 to 29/12/2024 08:45
Amount: 147 MW
Constraint: NC-N_WLWLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122549MARKET INTERVENTION28/12/2024 06:58:56 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122514

Direction is cancelled from: 1900 hrs 28/12/2024

Manager NEM Real Time Operations
     