122496NON-CONFORMANCE26/12/2024 04:20:19 PM

NON-CONFORMANCE Region VIC1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA4
Duration: 26/12/2024 16:00 to 26/12/2024 16:20
Amount: -13 MW
Constraint: NC-V_LYA4

Auto-generated on behalf of Manager NEM Real Time Operations
     
122495RECLASSIFY CONTINGENCY26/12/2024 04:12:00 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 26/12/2024 16:11 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122494RECLASSIFY CONTINGENCY26/12/2024 04:11:57 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 26/12/2024 16:11 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122493NON-CONFORMANCE26/12/2024 03:55:18 PM

NON-CONFORMANCE Region SA1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 26/12/2024 15:50 to 26/12/2024 15:55
Amount: 14 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122490MINIMUM SYSTEM LOAD26/12/2024 02:41:29 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

Update to Market Notice 122466 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 01/01/2025 to 1330 hrs 01/01/2025. Minimum regional demand is forecast to be 1474 MW at 1300 hrs.


Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
122489MINIMUM SYSTEM LOAD26/12/2024 02:39:52 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 29/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1730 MW
- MSL2 - 1230 MW
- MSL3 - 730 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 29/12/2024 to 1400 hrs 29/12/2024. Minimum regional demand is forecast to be 1489 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
122488NON-CONFORMANCE26/12/2024 01:10:18 PM

NON-CONFORMANCE Region SA1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TBSF1
Duration: 26/12/2024 09:35 to 26/12/2024 13:10
Amount: 17 MW
Constraint: NC-S_TBSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122486PRICES UNCHANGED25/12/2024 05:36:41 PM

[EventId:202412251705_confirmed] Prices for interval 25-Dec-2024 17:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:05.

In accordance with Market Notice 122475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122485PRICES UNCHANGED25/12/2024 05:35:28 PM

[EventId:202412251730_confirmed] Prices for interval 25-Dec-2024 17:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:30.

In accordance with Market Notice 122480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     