Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Sunday, 16 March 2025
NON-CONFORMANCE NSW1 Region Sunday, 16 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/03/2025 18:15 to 16/03/2025 18:20
Amount: -10 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 16/03/2025
Non-credible contingency event - QLD region - 16/03/2025
At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 15 March 2025
NON-CONFORMANCE SA1 Region Saturday, 15 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LADBROK2
Duration: 15/03/2025 17:00 to 15/03/2025 17:05
Amount: -9 MW
Constraint: NC-S_LADBROK2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 15 March 2025
NON-CONFORMANCE SA1 Region Saturday, 15 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LADBROK1
Duration: 15/03/2025 17:00 to 15/03/2025 17:05
Amount: -7 MW
Constraint: NC-S_LADBROK1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.
The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0101257 - Frequency Performance Payments Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025
NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF2
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 62 MW
Constraint: NC-N_NEWENSF2
Auto-generated on behalf of Manager NEM Real Time Operations