NON-CONFORMANCE Region QLD1 Friday, 4 April 2025
NON-CONFORMANCE QLD1 Region Friday, 4 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 04/04/2025 05:55 to 04/04/2025 06:20
Amount: 77 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 4 April 2025
NON-CONFORMANCE NSW1 Region Friday, 4 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP2
Duration: 04/04/2025 04:45 to 04/04/2025 04:55
Amount: -26 MW
Constraint: NC-N_MP2
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 04/04/2025
Non-credible contingency event - QLD region - 04/04/2025
At 0152 hrs the Ross - Townsville South No 7156 and 7249 132kV lines tripped and auto reclosed.
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: QLD
Elements: Ross - Townsville South No 7156 and 7249 132kV lines.
Duration: 0152 hrs 04/04/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 3 April 2025
NON-CONFORMANCE QLD1 Region Thursday, 3 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: W/HOE#2
Duration: 03/04/2025 19:05 to 03/04/2025 19:15
Amount: -13 MW
Constraint: NC-Q_W/HOE#2
Auto-generated on behalf of Manager NEM Real Time Operations
Create Market Notice - Completed - CHG0099569 - Maintenance on Gas B2B Hub databases
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Create Market Notice - Inital - CHG0102439 - NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)
Change Start Date & Time: 07/04/2025 09:00:00
Change End Date & Time: 07/04/2025 12:00:00
Outage Start Date & Time: 07/04/2025 09:00:00
Outage End Date & Time: 07/04/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities
Create Market Notice - Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:
3/04/2025
7/04/2025
8/04/2025
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Create Market Notice - Completed - CHG0102343 - Frequency Performance Payments (FPP) Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments (FPP) Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region QLD1 Wednesday, 2 April 2025
NON-CONFORMANCE QLD1 Region Wednesday, 2 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 02/04/2025 17:35 to 02/04/2025 22:40
Amount: -43 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations