Update to system strength requirements in North Queensland
Refer to market notice 121468
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.
A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I
AEMO Operations
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124043
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 03/02/2025
Non-credible contingency event - TAS region - 03/02/2025
At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 23/01/2025
Update - Non-credible contingency event - NSW region - 23/01/2025
Refer AEMO Electricity Market Notice 123613
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: NSW
Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 23/01/2025
Non-credible contingency event - NSW region - 23/01/2025
At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 15/01/2025
Update - Non-credible contingency event - NSW region - 15/01/2025
Refer AEMO Electricity Market Notice 123354
At 1458 hrs the Tomago - Taree (963) 132kV line was returned to service. The Tomago - Brandy Hill (9C6) 132kV line was returned to service on 16/01/2025.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 17/01/2025
Update - Non-credible contingency event - NSW region - 17/01/2025
Refer AEMO Electricity Market Notice 123406
At 1345 hrs the Buronga 330 kV B Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update Non-credible contingency event - NSW region - 17/01/2025
Update Non-credible contingency event - NSW region - 17/01/2025
Refer AEMO Electricity Market Notice 123404
At 0825 hrs the Buronga 330 kV B Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 17/01/2025
Non-credible contingency event - NSW region - 17/01/2025
At 0825 hrs the Buronga 330 kV B Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations