Market Notices

124340RECLASSIFY CONTINGENCY08/02/2025 09:33:25 AM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 08/02/2025 09:33 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124338PRICES UNCHANGED08/02/2025 07:55:29 AM

[EventId:202502080735_confirmed] Prices for interval 08-Feb-2025 07:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:35.

In accordance with Market Notice 124327 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124337PRICES UNCHANGED08/02/2025 07:55:28 AM

[EventId:202502080755_confirmed] Prices for interval 08-Feb-2025 07:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:55.

In accordance with Market Notice 124332 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124336PRICES UNCHANGED08/02/2025 07:55:27 AM

[EventId:202502080750_confirmed] Prices for interval 08-Feb-2025 07:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:50.

In accordance with Market Notice 124330 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124335PRICES UNCHANGED08/02/2025 07:55:26 AM

[EventId:202502080745_confirmed] Prices for interval 08-Feb-2025 07:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:45.

In accordance with Market Notice 124329 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124334PRICES UNCHANGED08/02/2025 07:55:24 AM

[EventId:202502080740_confirmed] Prices for interval 08-Feb-2025 07:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:40.

In accordance with Market Notice 124328 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124333PRICES UNCHANGED08/02/2025 07:55:25 AM

[EventId:202502080730_confirmed] Prices for interval 08-Feb-2025 07:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:30.

In accordance with Market Notice 124326 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124331PRICES UNCHANGED08/02/2025 07:50:16 AM

[EventId:202502080725_confirmed] Prices for interval 08-Feb-2025 07:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0750 hrs on 8 February 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Feb-2025 07:25.

In accordance with Market Notice 124325 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124324RECLASSIFY CONTINGENCY08/02/2025 06:24:45 AM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 08/02/2025 06:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124323

Auto-generated on behalf of Manager NEM Real Time Operations
     