NON-CONFORMANCE Region QLD1 Saturday, 7 December 2024
NON-CONFORMANCE QLD1 Region Saturday, 7 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 07/12/2024 18:45 to 07/12/2024 18:50
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121588 is cancelled at 1415 hrs 07/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121525
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 08/12/2024.
The direction update is issued at 1600 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121585 is cancelled at 1300 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 807 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 07/12/2024 to 1900 hrs 07/12/2024.
The forecast capacity reserve requirement is 1766 MW.
The minimum capacity reserve available is 1725 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121563 is cancelled at 0710 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121558 has been updated at 0645 hrs to the following:
[1.] From 1730 hrs 07/12/2024 to 1830 hrs 07/12/2024.
The forecast capacity reserve requirement is 1786 MW.
The minimum capacity reserve available is 1760 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121550 has been updated at 0400 hrs to the following:
[1.] From 1630 hrs 07/12/2024 to 1900 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1284 MW.
Manager NEM Real Time Operations