NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 20/02/2025 02:20 to 20/02/2025 03:00
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025
NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 19/02/2025
A planned outage of South Morang - Dederang No.1 330kV line series capacitor in the VIC region was scheduled from 0449 hrs 04/02/2025 to 1700 hrs 31/03/2025.
The outage has been completed and South Morang - Dederang No.1 330kV line series capacitor returned to service at 1205 hrs 19/02/2025
Constraint set(s) revoked: V-SMSC
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 15 February 2025
NON-CONFORMANCE QLD1 Region Saturday, 15 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 15/02/2025 15:50 to 15/02/2025 15:55
Amount: 15 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 15 February 2025
NON-CONFORMANCE QLD1 Region Saturday, 15 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MIDDLSF1
Duration: 15/02/2025 10:50 to 15/02/2025 11:45
Amount: 20 MW
Constraint: NC-Q_MIDDLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 14 February 2025
NON-CONFORMANCE QLD1 Region Friday, 14 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 14/02/2025 22:55 to 14/02/2025 23:00
Amount: 28 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
At 1738 hrs 13/02/2025 there was an unplanned outage of the Greenbank 275kV SVC.
The following constraint set(s) invoked at 1745 hrs 13/02/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025
Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025
A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.
The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025
Constraint set(s) revoked: N-X_MBTE_2
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025
Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025
At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.
The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations