Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/03/2025 to 1600 hrs 06/03/2025.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1635 hrs 05/03/2025
Constraint set(s) revoked: N-LDTM_82
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
At 1603 hrs 05/03/2025 there was an unplanned outage of Ewingsdale-Mullumbimby 9G5 132kV line.
The following constraint set(s) invoked at 1615 hrs 05/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 1040 hrs 05/03/2025
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202503041040_review] Prices for interval 04-Mar-2025 10:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503041035_review] Prices for interval 04-Mar-2025 10:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503041030_review] Prices for interval 04-Mar-2025 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503041025_review] Prices for interval 04-Mar-2025 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503041020_review] Prices for interval 04-Mar-2025 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503041015_review] Prices for interval 04-Mar-2025 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 4 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs