[EventId:202504101900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 April 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 10 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Refer to market notice: 126477
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 10 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504101725_review] Prices for interval 10-Apr-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101720_review] Prices for interval 10-Apr-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101715_review] Prices for interval 10-Apr-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 April 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 10 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504101710_review] Prices for interval 10-Apr-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_review] Prices for interval 10-Apr-2025 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101700_review] Prices for interval 10-Apr-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Release of PEC-1 and combined V-SA limits - 11 April 2025
Refer to market notice 123956
AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.
The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.
With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.