Market Notices

123639NON-CONFORMANCE23/01/2025 07:10:20 PM

NON-CONFORMANCE Region NSW1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 23/01/2025 19:05 to 23/01/2025 19:10
Amount: -25 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123638NON-CONFORMANCE23/01/2025 05:30:16 PM

NON-CONFORMANCE Region NSW1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 23/01/2025 17:25 to 23/01/2025 17:30
Amount: 15 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123621NON-CONFORMANCE23/01/2025 10:25:24 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 08:40 to 23/01/2025 10:25
Amount: -35 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123616NON-CONFORMANCE23/01/2025 06:05:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 05:50 to 23/01/2025 06:05
Amount: 38 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123615POWER SYSTEM EVENTS23/01/2025 03:09:25 AM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123613

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123598RESERVE NOTICE22/01/2025 07:44:15 PM

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123594RESERVE NOTICE22/01/2025 06:43:09 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
     
123564PRICES SUBJECT TO REVIEW22/01/2025 02:00:16 PM

[EventId:202501221405_review] Prices for interval 22-Jan-2025 14:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 22 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2025 14:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs