Inter-regional transfer limit variation - South East SVC - SA region - 27/12/2024
Inter-regional transfer limit variation - South East SVC - SA region - 27/12/2024
At 1452 hrs 27/12/2024 there was an unplanned outage of the South East SVC.
The following constraint set(s) invoked at 1500 hrs 27/12/2024
S-SE_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 27 December 2024
NON-CONFORMANCE VIC1 Region Friday, 27 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA3
Duration: 27/12/2024 01:05 to 27/12/2024 01:15
Amount: 28 MW
Constraint: NC-V_LYA3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 26 December 2024
NON-CONFORMANCE VIC1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA4
Duration: 26/12/2024 16:00 to 26/12/2024 16:20
Amount: -13 MW
Constraint: NC-V_LYA4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 26 December 2024
NON-CONFORMANCE SA1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 26/12/2024 15:50 to 26/12/2024 15:55
Amount: 14 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 26 December 2024
NON-CONFORMANCE SA1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TBSF1
Duration: 26/12/2024 09:35 to 26/12/2024 13:10
Amount: 17 MW
Constraint: NC-S_TBSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all of Directlink.
The following constraint set was invoked at 0840 hrs 26/12/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202412251705_confirmed] Prices for interval 25-Dec-2024 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:05.
In accordance with Market Notice 122475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251730_confirmed] Prices for interval 25-Dec-2024 17:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:30.
In accordance with Market Notice 122480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251725_confirmed] Prices for interval 25-Dec-2024 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:25.
In accordance with Market Notice 122479 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.