Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124097
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 05/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 06/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1300 hrs 06/02/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 124096
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 05/02/2025.
The direction update is issued at 1315 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1733 MW.
The minimum capacity reserve available is 1581 MW.
[2.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1212 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1754 MW.
The minimum capacity reserve available is 1560 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124146 is cancelled at 1014 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1292 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124144 is cancelled at 0814 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1353 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124119 has been updated at 1715 hrs 04/02/2025 to the following:
[1.] From 1730 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1639 MW.
The minimum capacity reserve available is 1108 MW.
Manager NEM Real Time Operations