Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Thursday, 23 January 2025
NON-CONFORMANCE NSW1 Region Thursday, 23 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 23/01/2025 17:25 to 23/01/2025 17:30
Amount: 15 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1900 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 830 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123523 is cancelled at 1400 hrs 23/01/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 123579
TORRB3 TORRENS ISLAN at 0400 hrs 24/01/2025 to Remain synchronised and follow dispatch targets.
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/01/2025.
The direction update is issued at 1500 hrs 23/01/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123618
PPCCGT PELICAN POINT at 1800 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1730 hrs 24/01/2025.
The direction update is issued at 1500 hrs 23/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025
NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 23/01/2025 08:40 to 23/01/2025 10:25
Amount: -35 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123582
PPCCGT PELICAN POINT at 1000 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is expected to stay in place until 1800 hrs 23/01/2025.
The direction update is issued at 0840 hrs 23/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025
NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 23/01/2025 05:50 to 23/01/2025 06:05
Amount: 38 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 23/01/2025
Update - Non-credible contingency event - NSW region - 23/01/2025
Refer AEMO Electricity Market Notice 123613
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: NSW
Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations