Market Notices

122715RECLASSIFY CONTINGENCY02/01/2025 10:56:51 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 02/01/2025 10:56 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
122707PRICES SUBJECT TO REVIEW02/01/2025 10:25:24 AM

[EventId:202501021030_review] Prices for interval 02-Jan-2025 10:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1025 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122706PRICES SUBJECT TO REVIEW02/01/2025 10:20:23 AM

[EventId:202501021025_review] Prices for interval 02-Jan-2025 10:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122704PRICES SUBJECT TO REVIEW02/01/2025 10:15:22 AM

[EventId:202501021020_review] Prices for interval 02-Jan-2025 10:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122703PRICES SUBJECT TO REVIEW02/01/2025 10:10:28 AM

[EventId:202501021015_review] Prices for interval 02-Jan-2025 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122702PRICES SUBJECT TO REVIEW02/01/2025 10:05:20 AM

[EventId:202501021010_review] Prices for interval 02-Jan-2025 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122700PRICES SUBJECT TO REVIEW02/01/2025 10:00:19 AM

[EventId:202501021005_review] Prices for interval 02-Jan-2025 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 2 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122696RECLASSIFY CONTINGENCY02/01/2025 05:39:25 AM

Cancellation of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Cancellation time: 02/01/2025 05:39

Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 122693

Auto-generated on behalf of Manager NEM Real Time Operations
     
122694RECLASSIFY CONTINGENCY02/01/2025 04:13:39 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 122691 (Severe Space Weather) is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 0410 hrs 02/01/2025.

Manager NEM Real Time Operations
     