125353NON-CONFORMANCE07/03/2025 01:00:15 AM

NON-CONFORMANCE Region QLD1 Friday, 7 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 7 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CPP_4
Duration: 07/03/2025 00:30 to 07/03/2025 01:00
Amount: -21 MW
Constraint: NC-Q_CPP_4

Auto-generated on behalf of Manager NEM Real Time Operations
     
125343SETTLEMENTS RESIDUE06/03/2025 06:20:24 PM

[EventId:202503061820_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 March 2025 18:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 6 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.

Refer to market notice: 125341

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1820 hrs on 6 March 2025.

This is an AEMO autogenerated Market Notice.
     
125341SETTLEMENTS RESIDUE06/03/2025 04:00:36 PM

[EventId:202503061600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 March 2025 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 6 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 6 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125320NON-CONFORMANCE06/03/2025 01:35:23 PM

NON-CONFORMANCE Region VIC1 Thursday, 6 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 6 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 06/03/2025 13:20 to 06/03/2025 13:35
Amount: 9 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125319PRICES SUBJECT TO REVIEW06/03/2025 01:30:16 PM

[EventId:202503061335_review] Prices for interval 06-Mar-2025 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125318PRICES SUBJECT TO REVIEW06/03/2025 01:25:21 PM

[EventId:202503061330_review] Prices for interval 06-Mar-2025 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125317PRICES SUBJECT TO REVIEW06/03/2025 01:20:21 PM

[EventId:202503061325_review] Prices for interval 06-Mar-2025 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125316PRICES SUBJECT TO REVIEW06/03/2025 01:15:24 PM

[EventId:202503061320_review] Prices for interval 06-Mar-2025 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125314PRICES SUBJECT TO REVIEW06/03/2025 01:10:23 PM

[EventId:202503061315_review] Prices for interval 06-Mar-2025 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 6 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm