Market Notices

124653SETTLEMENTS RESIDUE14/02/2025 09:05:27 AM

[EventId:202502140905_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 09:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0905 hrs on 14 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0905 hrs on 14 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124622INTER-REGIONAL TRANSFER13/02/2025 05:52:57 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025

At 1738 hrs 13/02/2025 there was an unplanned outage of the Greenbank 275kV SVC.

The following constraint set(s) invoked at 1745 hrs 13/02/2025
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124617INTER-REGIONAL TRANSFER13/02/2025 02:53:56 PM

Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025

A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.

The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025

Constraint set(s) revoked: N-X_MBTE_2

Manager NEM Real Time Operations
     
124586RESERVE NOTICE13/02/2025 10:47:48 AM

PDPASA - Update of the suspect Lack Of Reserve Level 2 (LOR2) condition in the QLD Region on 13/02/2025

AEMO ELECTRICITY MARKET NOTICE

The suspect LOR2 condition advised in AEMO Electricity Market Notice No. 124585 has been reviewed.

AEMO considers this forecast LOR2 condition invalid

No LOR2 condition is currently forecast for the QLD region.

Manager NEM Real Time Operation
     
124585RESERVE NOTICE13/02/2025 06:45:48 AM

PDPASA - Suspect Lack Of Reserve Level 2 (LOR2) in the QLD Region on 13/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there is a suspect Forecast LOR2 condition for the QLD region for the following period[s]:

[1.] From 1830 hrs 13/02/2025 to 1930 hrs 13/02/2025.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 480 MW.

AEMO is currently investigating this LOR2 forecast condition to confirm whether they are valid.

Manager NEM Real Time Operations
     
124579RESERVE NOTICE12/02/2025 08:44:30 PM

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.

Manager NEM Real Time Operations
     
124572RESERVE NOTICE12/02/2025 06:53:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW

Manager NEM Real Time Operations
     
124477INTER-REGIONAL TRANSFER11/02/2025 11:27:16 PM

Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025

At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.

The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124472INTER-REGIONAL TRANSFER11/02/2025 06:00:41 PM

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.

The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME

This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     