[EventId:202502221505_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 February 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 22 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1505 hrs on 22 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502211230_review] Prices for interval 21-Feb-2025 12:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1225 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502211225_review] Prices for interval 21-Feb-2025 12:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502211220_review] Prices for interval 21-Feb-2025 12:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502211215_review] Prices for interval 21-Feb-2025 12:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1210 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502211210_review] Prices for interval 21-Feb-2025 12:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502211205_review] Prices for interval 21-Feb-2025 12:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 21 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Feb-2025 12:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - NSW region - 21/02/2025
Update - Non-credible contingency event - NSW region - 21/02/2025
Refer AEMO Electricity Market Notice 124944
At 1030 hrs the Capital WF A and C 330kV Buses were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
[EventId:202502201830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 20 February 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 20 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 20 February 2025.
Refer to market notice: 124950
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 20 February 2025.