[EventId:202502190940_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 19 February 2025 09:40
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0940 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502190945_review] Prices for interval 19-Feb-2025 09:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 19 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Feb-2025 09:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502190940_review] Prices for interval 19-Feb-2025 09:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 19 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Feb-2025 09:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502190930_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 19 February 2025 09:30
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 19 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Refer to market notice: 124856
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 0930 hrs on 19 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502190935_review] Prices for interval 19-Feb-2025 09:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 19 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Feb-2025 09:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502190835_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 19 February 2025 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0835 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502181825_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 18 February 2025 18:25
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 18 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 18 February 2025.
Refer to market notice: 124852
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1825 hrs on 18 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502181705_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 18 February 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 18 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 18 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1705 hrs on 18 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502181630_review] Prices for interval 18-Feb-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Feb-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.