125514SETTLEMENTS RESIDUE11/03/2025 08:30:33 AM

[EventId:202503110830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 March 2025 08:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 11 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0830 hrs on 11 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125507PRICES SUBJECT TO REVIEW11/03/2025 08:15:17 AM

[EventId:202503110820_review] Prices for interval 11-Mar-2025 08:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125506PRICES SUBJECT TO REVIEW11/03/2025 08:10:17 AM

[EventId:202503110815_review] Prices for interval 11-Mar-2025 08:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0810 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125505PRICES SUBJECT TO REVIEW11/03/2025 08:05:18 AM

[EventId:202503110810_review] Prices for interval 11-Mar-2025 08:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0805 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125504PRICES SUBJECT TO REVIEW11/03/2025 08:00:21 AM

[EventId:202503110805_review] Prices for interval 11-Mar-2025 08:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125503PRICES SUBJECT TO REVIEW11/03/2025 07:55:17 AM

[EventId:202503110800_review] Prices for interval 11-Mar-2025 08:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125502PRICES SUBJECT TO REVIEW11/03/2025 07:50:25 AM

[EventId:202503110755_review] Prices for interval 11-Mar-2025 07:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0750 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 07:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125431MARKET INTERVENTION09/03/2025 01:27:46 PM

Cancellation - AEMO Intervention Event - SA region 08/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 08/03/2025

Refer to Market Notice 125396

The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.


Manager NEM Real Time Operations
     
125426MARKET INTERVENTION09/03/2025 01:25:15 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125398

Direction is cancelled from: 1330 hrs 09/03/2025

Manager NEM Real Time Operations
     