Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024
NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WHITSF1
Duration: 24/11/2024 09:25 to 24/11/2024 10:35
Amount: 53 MW
Constraint: NC-Q_WHITSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 22 November 2024
NON-CONFORMANCE NSW1 Region Friday, 22 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 22/11/2024 08:05 to 22/11/2024 08:25
Amount: -73 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 20 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 20 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 20/11/2024 06:35 to 20/11/2024 15:35
Amount: -45 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
INC0138395 - P1 - Electricity Market Management System service- RESOLVED
This incident has been uplifted to a P1.
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138395 - Electricity Market Management System service- RESOLVED
The service interruption relating to the Electricity Market Management System service has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
NON-CONFORMANCE Region NSW1 Tuesday, 19 November 2024
NON-CONFORMANCE NSW1 Region Tuesday, 19 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: AVLSF1
Duration: 19/11/2024 10:40 to 19/11/2024 10:50
Amount: 19 MW
Constraint: NC-N_AVLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 18 November 2024
NON-CONFORMANCE NSW1 Region Monday, 18 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 18/11/2024 17:25 to 18/11/2024 17:40
Amount: -13 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations