Market Notices

125081CONSTRAINTS25/02/2025 08:31:51 AM

Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines

AEMO ELECTRICITY MARKET NOTICE

Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.

Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.

N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051

Ben Blake
AEMO Operations
     
124971NON-CONFORMANCE21/02/2025 12:10:28 PM

NON-CONFORMANCE Region VIC1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MCKAY1
Duration: 21/02/2025 12:00 to 21/02/2025 12:10
Amount: -54 MW
Constraint: NC-V_MCKAY1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124969NON-CONFORMANCE21/02/2025 12:05:21 PM

NON-CONFORMANCE Region SA1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/02/2025 11:50 to 21/02/2025 12:05
Amount: -19 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124965NON-CONFORMANCE21/02/2025 10:20:19 AM

NON-CONFORMANCE Region QLD1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANGARR1
Duration: 21/02/2025 09:40 to 21/02/2025 10:20
Amount: 72 MW
Constraint: NC-Q_GANGARR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124941NON-CONFORMANCE20/02/2025 02:25:16 PM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CAPBES1
Duration: 20/02/2025 14:15 to 20/02/2025 14:25
Amount: 70 MW
Constraint: NC-N_CAPBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124914NON-CONFORMANCE20/02/2025 07:55:28 AM

NON-CONFORMANCE Region SA1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 19 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CLEMGPWF
Duration: 19/02/2025 17:30 to 20/02/2025 07:55
Amount: 15 MW
Constraint: NC-S_CLEMGPWF

Auto-generated on behalf of Manager NEM Real Time Operations
     
124913NON-CONFORMANCE20/02/2025 03:45:14 AM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 20/02/2025 03:30 to 20/02/2025 03:45
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124912NON-CONFORMANCE20/02/2025 03:00:19 AM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 20/02/2025 02:20 to 20/02/2025 03:00
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124879NON-CONFORMANCE19/02/2025 12:10:21 PM

NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     