123464RESERVE NOTICE19/01/2025 05:24:36 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1530 hrs 24/01/2025 to 1600 hrs 24/01/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 247 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123451POWER SYSTEM EVENTS18/01/2025 04:19:58 PM

Update - Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 15/01/2025

Refer AEMO Electricity Market Notice 123354

At 1458 hrs the Tomago - Taree (963) 132kV line was returned to service. The Tomago - Brandy Hill (9C6) 132kV line was returned to service on 16/01/2025.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
123445POWER SYSTEM EVENTS18/01/2025 02:06:59 PM

Update - Non-credible contingency event - NSW region - 17/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 17/01/2025

Refer AEMO Electricity Market Notice 123406

At 1345 hrs the Buronga 330 kV B Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
123406POWER SYSTEM EVENTS17/01/2025 02:46:41 PM

Update Non-credible contingency event - NSW region - 17/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update Non-credible contingency event - NSW region - 17/01/2025

Refer AEMO Electricity Market Notice 123404

At 0825 hrs the Buronga 330 kV B Bus tripped.
AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
123404POWER SYSTEM EVENTS17/01/2025 10:11:09 AM

Non-credible contingency event - NSW region - 17/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 17/01/2025

At 0825 hrs the Buronga 330 kV B Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123382INTER-REGIONAL TRANSFER16/01/2025 02:40:39 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 16/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_BRIS_569B1432 from 1425 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
123354POWER SYSTEM EVENTS15/01/2025 10:45:07 PM

Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 15/01/2025

At 2019 hrs the Tomago - Taree (963) 132kV line and the Tomago - Brandy Hill (96C) 132kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of 80 MW of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123334INTER-REGIONAL TRANSFER15/01/2025 05:12:38 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5699E75F from 1655 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
VIC1-NSW1

Manager NEM Real Time Operations
     
123276INTER-REGIONAL TRANSFER15/01/2025 02:21:49 PM

Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025

At 1400 hrs 15/01/2025 there was an unplanned outage of Murray - Lower Tumut 330 kV 66 line.

The following constraint set(s) invoked at 1415 hrs 15/01/2025
I-LTMS

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,V-S-MNSP1,NSW1-QLD1,T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     