126722GENERAL NOTICE24/04/2025 03:59:43 PM

Release of QNI limit from NSW to Qld - 29th April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 124749.

AEMO, Transgrid, Powerlink have reviewed the test results following the QNI minor testing on 16th February 2025. The next hold point can now be released.

The hold point of 950 MW from NSW to Qld will be implemented as of 1000 hrs 29th April 2025.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
126715NON-CONFORMANCE24/04/2025 01:55:19 PM

NON-CONFORMANCE Region SA1 Thursday, 24 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 24 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 24/04/2025 13:50 to 24/04/2025 13:55
Amount: 143 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126690NON-CONFORMANCE23/04/2025 10:00:21 AM

NON-CONFORMANCE Region NSW1 Wednesday, 23 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 23 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JEMALNG1
Duration: 23/04/2025 08:50 to 23/04/2025 10:00
Amount: 38 MW
Constraint: NC-N_JEMALNG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126599NON-CONFORMANCE19/04/2025 02:30:19 PM

NON-CONFORMANCE Region QLD1 Saturday, 19 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 19 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 19/04/2025 14:20 to 19/04/2025 14:30
Amount: 15 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126472NON-CONFORMANCE10/04/2025 03:35:16 PM

NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126466GENERAL NOTICE10/04/2025 11:12:18 AM

Release of PEC-1 and combined V-SA limits - 11 April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 123956

AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.

The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.

With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
126462NON-CONFORMANCE09/04/2025 07:05:12 PM

NON-CONFORMANCE Region NSW1 Wednesday, 9 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 9 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 09/04/2025 19:00 to 09/04/2025 19:05
Amount: -38 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
126414NON-CONFORMANCE07/04/2025 08:05:13 AM

NON-CONFORMANCE Region QLD1 Monday, 7 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 7 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 07/04/2025 07:55 to 07/04/2025 08:05
Amount: 16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126380NON-CONFORMANCE06/04/2025 12:55:19 PM

NON-CONFORMANCE Region SA1 Sunday, 6 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 6 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 06/04/2025 12:40 to 06/04/2025 12:55
Amount: 16 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm