Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines
Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.
Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.
N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051
Ben Blake
AEMO Operations
[EventId:202502241730_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Refer to market notice: 125075
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1730 hrs on 24 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502241540_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 15:40
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 24 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1540 hrs on 24 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502241530_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 24 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Refer to market notice: 125071
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1530 hrs on 24 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502241435_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 24 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1435 hrs on 24 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502241300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 24 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Refer to market notice: 125068
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 24 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502241105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 24 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 24 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502231510_review] Prices for interval 23-Feb-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 23 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502231505_review] Prices for interval 23-Feb-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.