Market Notices

124143RESERVE NOTICE05/02/2025 04:36:11 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124066 has been updated at 0423 hrs 05/02/2025 to the following:

[1.] From 1600 hrs 07/02/2025 to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 678 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
124137RESERVE NOTICE04/02/2025 07:50:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124131 is cancelled at 1930 hrs 04/02/2025.

Manager NEM Real Time Operations
     
124131RESERVE NOTICE04/02/2025 05:46:30 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1161 MW

Manager NEM Real Time Operations
     
124129RESERVE NOTICE04/02/2025 05:40:03 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124119 has been updated at 1715 hrs 04/02/2025 to the following:

[1.] From 1730 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1639 MW.
The minimum capacity reserve available is 1108 MW.

Manager NEM Real Time Operations
     
124127RESERVE NOTICE04/02/2025 05:27:13 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124121 is cancelled at 1715 hrs 04/02/2025.

Manager NEM Real Time Operations
     
124121RESERVE NOTICE04/02/2025 05:02:14 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124090 has been updated at 1620 hrs 04/02/2025 to the following:

[1.] From 1730 hrs 04/02/2025 to 1830 hrs 04/02/2025.
The forecast capacity reserve requirement is 948 MW.
The minimum capacity reserve available is 664 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
124119RESERVE NOTICE04/02/2025 04:36:56 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124091 has been updated at 1620 hrs 04/02/2025 to the following:

[1.] From 1630 hrs 04/02/2025 to 1730 hrs 04/02/2025.
The forecast capacity reserve requirement is 1699 MW.
The minimum capacity reserve available is 978 MW.

[2.] From 1830 hrs 04/02/2025 to 2000 hrs 04/02/2025.
The forecast capacity reserve requirement is 1649 MW.
The minimum capacity reserve available is 947 MW.

Manager NEM Real Time Operations
     
124097MARKET INTERVENTION04/02/2025 03:51:45 PM

Direction - SA region 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 04/02/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1545 hrs on 04/02/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
124096MARKET INTERVENTION04/02/2025 03:45:34 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 124056


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1540 hrs 04/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0030 hrs 05/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 06/02/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm