122272MARKET INTERVENTION19/12/2024 03:02:42 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 20/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122259MARKET INTERVENTION19/12/2024 03:01:30 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122199

Direction is cancelled from: 1500 hrs 19/12/2024

Manager NEM Real Time Operations
     
122199MARKET INTERVENTION18/12/2024 03:59:20 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122110

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 19/12/2024.

The direction update is issued at 1600 hrs 18/12/2024.

Manager NEM Real Time Operations
     
122198MARKET INTERVENTION18/12/2024 03:58:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122111

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 19/12/2024.

The direction update is issued at 1600 hrs 18/12/2024.

Manager NEM Real Time Operations
     
122117RESERVE NOTICE17/12/2024 05:44:06 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122113RESERVE NOTICE17/12/2024 03:44:28 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW

Manager NEM Real Time Operations
     
122111MARKET INTERVENTION17/12/2024 04:31:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122013

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.

The direction update is issued at 1630 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122110MARKET INTERVENTION17/12/2024 04:30:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122012

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.

The direction update is issued at 1630 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122095RESERVE NOTICE17/12/2024 11:40:17 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122093 is cancelled at 1140 hrs 17/12/2024.

Manager NEM Real Time Operations
     