Non-credible contingency event - TAS region - 03/02/2025
Non-credible contingency event - TAS region - 03/02/2025
At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 3 February 2025
NON-CONFORMANCE NSW1 Region Monday, 3 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 31 January 2025
NON-CONFORMANCE NSW1 Region Friday, 31 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 30 January 2025
NON-CONFORMANCE NSW1 Region Thursday, 30 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 30/01/2025 06:45 to 30/01/2025 06:50
Amount: -14 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 29 January 2025
NON-CONFORMANCE NSW1 Region Wednesday, 29 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CAPBES1
Duration: 29/01/2025 08:35 to 29/01/2025 08:40
Amount: -100 MW
Constraint: NC-N_CAPBES1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 28 January 2025
NON-CONFORMANCE QLD1 Region Tuesday, 28 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 28/01/2025 17:55 to 28/01/2025 18:10
Amount: -17 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 27 January 2025
NON-CONFORMANCE SA1 Region Monday, 27 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 27/01/2025 15:40 to 27/01/2025 15:45
Amount: 12 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 27 January 2025
NON-CONFORMANCE QLD1 Region Monday, 27 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 27/01/2025 08:35 to 27/01/2025 08:50
Amount: 25 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 25 January 2025
NON-CONFORMANCE QLD1 Region Saturday, 25 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 25/01/2025 12:40 to 25/01/2025 13:10
Amount: 37 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations