NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025
NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123546 is cancelled at 0800 hrs 22/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 28/01/2025 to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 570 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123506
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 21/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2230 hrs 21/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 23/01/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 123504
TORRB3 TORRENS ISLAN at 0800 hrs 21/01/2025 to Remain synchronised and follow dispatch targets.
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/01/2025.
The direction update is issued at 1605 hrs 21/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123505
Direction is cancelled from: 1630 hrs 21/01/2025
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025
NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations