Market Notices

122451MARKET INTERVENTION24/12/2024 02:02:09 PM

Direction - SA region 24/12/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/12/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1405 hrs on 24/12/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
122448MARKET INTERVENTION24/12/2024 01:54:13 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122440

Direction is cancelled from: 1400 hrs 24/12/2024

Manager NEM Real Time Operations
     
122447MARKET INTERVENTION24/12/2024 11:31:06 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 122446

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 24/12/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122446MARKET INTERVENTION24/12/2024 10:57:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122441MARKET INTERVENTION23/12/2024 04:34:00 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122408

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122440MARKET INTERVENTION23/12/2024 04:32:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122407

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122408MARKET INTERVENTION22/12/2024 04:01:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122373

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122407MARKET INTERVENTION22/12/2024 04:00:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122372

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122373MARKET INTERVENTION21/12/2024 03:53:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122312

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/12/2024.

The direction update is issued at 1600 hrs 21/12/2024.

Manager NEM Real Time Operations
     