NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501211630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Refer to market notice: 123526
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 21 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501211450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 21 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 21 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025
NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501211330_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 21 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Refer to market notice: 123515
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1330 hrs on 21 January 2025.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - NSW Region - 21/01/2025
Refer Market notice: 123507
Network Augmentation Commissioned - NSW Region - 21/01/2025
Commissioned: Bundey to Buronga 330 kV (6F) line.
Buronga No. 5 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Update - Pre dispatch demand forecast error - NEM regions
Update - Pre dispatch demand forecast error - NEM regions
Refer market notice: 123513
The issue relating to the Pre dispatch demand forecast error has been resolved.
Manager NEM Real Time Operations
[EventId:202501211135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 21 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 21 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.