NON-CONFORMANCE Region NSW1 Wednesday, 9 April 2025
NON-CONFORMANCE NSW1 Region Wednesday, 9 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 09/04/2025 19:00 to 09/04/2025 19:05
Amount: -38 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126458 is cancelled at 1845 hrs 09/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1549 MW
The minimum capacity reserve available is 1164 MW
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Refer Market Notice 126440
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1430 hrs 09/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 10/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
The foreseeable circumstance identified in Market Notice 126418 is cancelled.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 08/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/04/2025
Cancellation - AEMO Intervention Event - SA region 06/04/2025
Refer to Market Notice 126384
The AEMO Intervention Event and all associated directions are cancelled from 1035 hrs on 07/04/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 126383
Direction is cancelled from: 1035 hrs 07/04/2025
Manager NEM Real Time Operations