CHG0101145 | Production | Planned Maintenance to Norwest Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router
Change Start Date & Time: 15/02/2025 10:00:00 AEST
Change End Date & Time: 15/02/2025 15:00:00 AEST
Outage Start Date & Time: 15/02/2025 11:00:00 AEST
Outage End Date & Time: 15/02/2025 13:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO NSW Datacentre if VPN connection is only terminating in NSW only.
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point 202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
A planned outage of Collector WF to Marulan No. 4 330 kV Line in the NSW region was scheduled from 0600 hrs 02/02/2025 to 1600 hrs 19/02/2025.
The outage has been completed and Collector WF to Marulan No. 4 330 kV Line returned to service at 1710 hrs 04/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
CHG0101137 | Completed | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025
At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.
The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0100610 | Completed | Production | Planned Maintenance to Brisbane Internet Router
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet Router
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.
The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA
The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.
The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations