Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 13 January 2025
NON-CONFORMANCE NSW1 Region Monday, 13 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Refer market notice: 123171
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR2) condition in the NSW region - 13/01/2025
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123176 is cancelled at 1815 hrs 13/01/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 13/01/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is forecast to exist until 1800 hrs
The capacity reserve required is 714 MW
The minimum reserve available is 560 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 13 January 2025
NON-CONFORMANCE QLD1 Region Monday, 13 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 13/01/2025 11:35 to 13/01/2025 13:50
Amount: 57 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 10 Jan 2025 to 14 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Jan, 14th Jan
VIC
Mildura Ap (39+ Deg C): 12th Jan, 13th Jan, 14th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region NSW1 Friday, 10 January 2025
NON-CONFORMANCE NSW1 Region Friday, 10 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 10/01/2025 09:45 to 10/01/2025 09:50
Amount: -24 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations