Market Notices

123213MARKET INTERVENTION14/01/2025 03:29:29 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123201

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 14/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123202SETTLEMENTS RESIDUE14/01/2025 01:00:24 PM

[EventId:202501141300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 January 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 14 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.

Refer to market notice: 123198

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 14 January 2025.

This is an AEMO autogenerated Market Notice.
     
123201MARKET INTERVENTION14/01/2025 01:09:01 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123198SETTLEMENTS RESIDUE14/01/2025 11:35:25 AM

[EventId:202501141135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 January 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 14 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 14 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123194NON-CONFORMANCE14/01/2025 06:00:15 AM

NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 14/01/2025 05:55 to 14/01/2025 06:00
Amount: -19 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123184SETTLEMENTS RESIDUE13/01/2025 07:45:27 PM

[EventId:202501131945_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 January 2025 19:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 13 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.

Refer to market notice: 123173

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1945 hrs on 13 January 2025.

This is an AEMO autogenerated Market Notice.
     
123182NON-CONFORMANCE13/01/2025 07:20:16 PM

NON-CONFORMANCE Region NSW1 Monday, 13 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 13 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123173SETTLEMENTS RESIDUE13/01/2025 05:06:01 PM

[EventId:202501131705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 January 2025 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 13 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 13 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123160MARKET INTERVENTION13/01/2025 03:11:55 PM

Cancellation - AEMO Intervention Event - SA region 12/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/01/2025

Refer to Market Notice 123112

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 13/01/2025.


Manager NEM Real Time Operations
     