126588RECLASSIFY CONTINGENCY18/04/2025 04:24:40 AM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 18/04/2025 04:24 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
126587RECLASSIFY CONTINGENCY18/04/2025 03:29:40 AM

Cancellation of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Cancellation time: 18/04/2025 03:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 126586

Auto-generated on behalf of Manager NEM Real Time Operations
     
126586RECLASSIFY CONTINGENCY18/04/2025 02:27:20 AM

Reclassification of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Duration: 18/04/2025 02:27 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
126585RECLASSIFY CONTINGENCY17/04/2025 11:54:41 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 17/04/2025 23:54

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 126584

Auto-generated on behalf of Manager NEM Real Time Operations
     
126584RECLASSIFY CONTINGENCY17/04/2025 10:52:16 PM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 17/04/2025 22:52 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
126583MARKET SYSTEMS17/04/2025 03:23:02 PM

CHG0102489 - Pre-Prod eMDM Maintenance Release

Change Number: CHG0102489

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 22/04/2025 13:00:00
Change End Date & Time: 22/04/2025 17:00:00
Outage Start Date & Time: 22/04/2025 13:00:00
Outage End Date & Time: 22/04/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126577INTER-REGIONAL TRANSFER16/04/2025 09:33:38 PM

Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025

At 2110 hrs 16/04/2025 there was an unplanned outage of Greenbank - Molendinar 8825 275kV line.

The following constraint set(s) invoked at 2120 hrs 16/04/2025
Q-GBMO_8824_8825

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126558INTER-REGIONAL TRANSFER14/04/2025 05:49:12 PM

Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025

A planned outage of the Collector -Yass 3L 330kV Line in the NSW region was scheduled from 0700 hrs 12/04/2025 to 1700 hrs 16/04/2025.

The outage has been completed and the Collector -Yass 3L 330kV Line returned to service at 1735 hrs 14/04/2025

Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
     
126502INTER-REGIONAL TRANSFER11/04/2025 04:07:53 PM

Inter-regional transfer limit variation - Greenbank SVC- QLD region - 11/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank SVC - QLD region - 11/04/2025

At 1600 hrs 11/04/2025 there was an unplanned outage of Greenbank SVC.

The following constraint set(s) invoked at 1605 hrs 11/04/2025
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.