125138INTER-REGIONAL TRANSFER01/03/2025 02:46:35 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 01/03/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_56D513DF from 1430 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
     
125127NON-CONFORMANCE27/02/2025 09:35:13 PM

NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#1
Duration: 27/02/2025 21:25 to 27/02/2025 21:35
Amount: -11 MW
Constraint: NC-Q_TARONG#1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125123NON-CONFORMANCE27/02/2025 06:50:18 PM

NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WDBESS1
Duration: 27/02/2025 18:35 to 27/02/2025 18:50
Amount: -55 MW
Constraint: NC-Q_WDBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125112NON-CONFORMANCE27/02/2025 08:55:25 AM

NON-CONFORMANCE Region NSW1 Thursday, 27 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 27 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 27/02/2025 08:45 to 27/02/2025 08:55
Amount: -7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125098NON-CONFORMANCE26/02/2025 12:40:25 PM

NON-CONFORMANCE Region NSW1 Wednesday, 26 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 26 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BERYLSF1
Duration: 26/02/2025 12:15 to 26/02/2025 12:40
Amount: 76 MW
Constraint: NC-N_BERYLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125083NON-CONFORMANCE25/02/2025 11:00:18 AM

NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125082NON-CONFORMANCE25/02/2025 10:20:17 AM

NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4

Auto-generated on behalf of Manager NEM Real Time Operations
     
125081CONSTRAINTS25/02/2025 08:31:51 AM

Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines

AEMO ELECTRICITY MARKET NOTICE

Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.

Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.

N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051

Ben Blake
AEMO Operations
     
125026INTER-REGIONAL TRANSFER23/02/2025 03:44:24 AM

Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025

At 0305 hrs 23/02/2025 there was an unplanned outage of BassLink Harmonic Filter.

The following constraint set(s) invoked at 0305 hrs 23/02/2025
T-BLGC_HF_43MVAR

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm