Market Notices

123615POWER SYSTEM EVENTS23/01/2025 03:09:25 AM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123613

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
Duration: 0250 hrs 23/01/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123601INTER-REGIONAL TRANSFER22/01/2025 08:11:14 PM

Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025

Refer to MN 123588

In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) ,

AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until 1845 hs 22/01/2025.

This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1

Manager NEM Real Time Operations
     
123598RESERVE NOTICE22/01/2025 07:44:15 PM

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123597INTER-REGIONAL TRANSFER22/01/2025 07:53:16 PM

Inter-regional transfer limit variation -Lismore No1 SVC - NSW region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore No1 SVC - NSW region - 22/01/2025

A planned outage of Lismore No1 SVC in the NSW region was scheduled from 0620 hrs 08/01/2025 to 1600 hrs 24/01/2025.

The outage has been completed and Lismore No1 SVC returned to service at 1900 hrs 22/01/2025

Constraint set(s) revoked: N-LS_VC1

Manager NEM Real Time Operations
     
123594RESERVE NOTICE22/01/2025 06:43:09 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
     
123588INTER-REGIONAL TRANSFER22/01/2025 05:29:02 PM

Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 25/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) , AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1

Manager NEM Real Time Operations
     
123582MARKET INTERVENTION22/01/2025 04:01:56 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 22/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 23/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 23/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123580MARKET INTERVENTION23/01/2025 03:40:17 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123529

Direction is cancelled from: 0400 hrs 23/01/2025

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm