Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all of Directlink.
The following constraint set was invoked at 0840 hrs 26/12/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 23/12/2024
Update - Non-credible contingency event - SA region - 23/12/2024
Refer AEMO Electricity Market Notice 122442
At 2036 hrs the Happy Valley - Morphett Vale East and the Morphett Vale - Cherry Gardens 275kV lines were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 23/12/2024
Non-credible contingency event - SA region - 23/12/2024
At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 23 December 2024
NON-CONFORMANCE QLD1 Region Monday, 23 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.
The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 20 December 2024
NON-CONFORMANCE NSW1 Region Friday, 20 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations