125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125609RESERVE NOTICE13/03/2025 06:41:32 PM

Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125606 is cancelled at 1840 hrs 13/03/2025.

Manager NEM Real Time Operations
     
125606RESERVE NOTICE13/03/2025 05:45:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1668 MW
The minimum capacity reserve available is 1530 MW

Manager NEM Real Time Operations
     
125560INTER-REGIONAL TRANSFER12/03/2025 02:20:15 PM

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.

The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025

Constraint set(s) revoked: N-X_MBTE_3

Manager NEM Real Time Operations
     
125543INTER-REGIONAL TRANSFER12/03/2025 07:03:39 AM

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.

The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125518INTER-REGIONAL TRANSFER11/03/2025 10:05:53 AM

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.

The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125513PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110755_confirmed] Prices for interval 11-Mar-2025 07:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 07:55.

In accordance with Market Notice 125502 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125512PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110820_confirmed] Prices for interval 11-Mar-2025 08:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:20.

In accordance with Market Notice 125507 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     