Filter by category
Filter by Date
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all of Directlink.
The following constraint set was invoked at 0840 hrs 26/12/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 23 December 2024
NON-CONFORMANCE QLD1 Region Monday, 23 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.
The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 20 December 2024
NON-CONFORMANCE NSW1 Region Friday, 20 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.
Manager NEM Real Time Operations