Filter by category
Filter by Date
CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region NSW1 Tuesday, 11 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/02/2025 13:55 to 11/02/2025 14:00
Amount: -11 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations
INC0140978 - ALERT - Frequency Performance Payments (FPP) System
ALERT - Frequency Performance Payments (FPP) System
AEMO experienced service interruption relating to Frequency Performance Payments (FPP) System. The FPP System was unable to calculate & publish Contribution Factors (CFs) from 14:36 Hrs AEST on 9/02/2025 till 09:34 Hrs AEST on 10/02/2025.
The service interruption relating to Frequency Performance Payments (FPP) System has now been resolved.
Default Contribution Factors (DCFs) will be applicable for the trading intervals where CFs were not calculated.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124399 is cancelled at 1749 hrs 09/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1171 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124305 is cancelled at 1940 hrs 07/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 936 MW