Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations
Request for Generator Recall Information for the period 27/11/2024 for Region QLD
Refer to AEMO Electricity Market Notice no. 120895.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for the period 27/11/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 120894, and 120892.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
[EventId:202411221115_confirmed] Prices for interval 22-Nov-2024 11:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1126 hrs on 22 November 2024
PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:15.
In accordance with Market Notice 120795 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $64.00 $25.81
QLD1 $62.79 $26.90
SA1 $8.61 $11.91
VIC1 $8.95 $12.00
LOWER1SEC
NSW1 $0.94 $0.10
QLD1 $0.94 $0.10
SA1 $0.94 $0.10
VIC1 $0.94 $0.10
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $9.99 $19.85
QLD1 $9.99 $19.85
SA1 $9.99 $19.85
VIC1 $9.99 $19.85
RAISE1SEC
NSW1 $0.84 $0.05
QLD1 $0.84 $0.05
SA1 $0.84 $0.05
TAS1 $0.84 $0.05
VIC1 $0.84 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.00 $0.01
QLD1 $0.00 $0.01
SA1 $0.00 $0.01
VIC1 $0.00 $0.01
RAISE6SEC
NSW1 $0.01 $0.00
QLD1 $0.01 $0.00
SA1 $0.01 $0.00
VIC1 $0.01 $0.00
RAISEREG
NSW1 $7.99 $1.00
QLD1 $7.99 $1.00
SA1 $7.99 $1.00
VIC1 $7.99 $1.00
This is an AEMO autogenerated Market Notice.
[EventId:202411221110_confirmed] Prices for interval 22-Nov-2024 11:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1117 hrs on 22 November 2024
PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:10.
In accordance with Market Notice 120794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $150.01 $25.81
QLD1 $143.43 $26.90
SA1 $53.81 $11.91
VIC1 $55.02 $12.00
LOWER5MIN
NSW1 $1.57 $0.39
QLD1 $1.57 $0.39
SA1 $1.57 $0.39
VIC1 $1.57 $0.39
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $20.90 $19.85
QLD1 $20.90 $19.85
SA1 $20.90 $19.85
VIC1 $20.90 $19.85
RAISE1SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
TAS1 $0.10 $0.05
VIC1 $0.10 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.05 $0.01
QLD1 $0.05 $0.01
SA1 $0.05 $0.01
VIC1 $0.05 $0.01
RAISE6SEC
NSW1 $0.10 $0.00
QLD1 $0.10 $0.00
SA1 $0.10 $0.00
VIC1 $0.10 $0.00
RAISEREG
NSW1 $5.00 $1.00
QLD1 $5.00 $1.00
SA1 $5.00 $1.00
VIC1 $5.00 $1.00
This is an AEMO autogenerated Market Notice.
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Prices for intervals on 05/09/2024 from 13:55 to 15:10 are now confirmed
Refer AEMO Electricity Market Notice 118149 and 118150.
PRICES ARE NOW REVISED to Market Suspension Pricing Schedule for trading intervals on 05/09/2024 from 1355 hrs to 1510 hrs.
Manager Electricity Market Monitoring
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 118149
AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1510 hrs on 05 September 2024.
AEMO has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.
Relevant Market Notices issued under this suspension: 118149