Wholesale Electricity Market Rules – Clause 2.10
Date of Notice: 21 July 2017
This notice informs all Rule Participants and interested parties (Consulted Persons) that AEMO has published a Procedure Change Proposal in respect of the revised Power System Operating Procedure: Dispatch and is conducting a consultation process in respect of this proposal.
This consultation is being carried out in accordance with the Procedure Change Process detailed in clause 2.10 of the Wholesale Electricity Market (WEM) Rules.
Matter under Consultation
The matters are related to clauses 7.6.10A and 7.13.5 of the WEM Rules, which commence on 1 October 2017 and which require AEMO to the process for Market Participants who have been assigned DSM Capacity Credits to provide AEMO with their consumption information.
Further details are provided in the Procedure Change Proposal and the proposed new Market Procedure published with this notice.
The Consultation Process
The consultation process is outlined below. Dates in italics are indicative only and subject to change.
Process Stage |
Date |
Closing date for submissions in response to the Procedure Change Proposal |
18 August 2017 |
Publication of Procedure Change Report |
28 September 2017 |
Proposed commencement of revised Market Procedure |
01 October 2017 |
Procedure Change Proposal documents
- Call for submissions on Procedure Change Proposal AEPC_2017_10 (210 KB, pdf)
- Procedure Change Proposal AEPC_2017_10 (430 KB, pdf)
- Proposed revised Market Procedure: Dispatch (670 KB, pdf)
Submissions
- Synergy - AEPC_2017_10 (141 KB, pdf)
Procedure Change report documents
- Procedure Change Report AEPC_2017_10 (210 KB, pdf)
- Power System Operating Procedure: Dispatch (clean version) (430 KB, pdf)
- Power System Operating Procedure: Dispatch (marked up version) (670 KB, pdf)