AusNet RIT-T PSCR: Maintaining reliable 330/220 kV transformation network services at South Morang Terminal Station

23/08/2024
Market Network Service Provider
StageProject Specification Consultation Report
ConvenorAEMO NSP
Initiated23/08/2024
Accepting submissions?No
Submissions close15/11/2024

AusNet is initiating this Regulatory Investment Test for Transmission (RIT-T) to investigate options that could allow continued delivery of safe and reliable transmission services. Publication of this Project Specification Consultation Report (PSCR) represents the first step in the RIT-T process in accordance with clause 5.16 of the National Electricity Rules (NER) and section 4.2 of the RIT-T Application Guidelines.

AusNet is investigating options that could allow continued delivery of safe and reliable 330/220 kV transformation network services at South Morang Terminal Station.

AusNet welcomes written submissions on the issues and the credible options presented in this PSCR.

Submissions should be emailed to rittconsultations@ausnetservices.com.au on or before 15 November 2024. In the subject field, please reference ‘RIT-T PSCR South Morang Terminal Station 330/220 kV transformer replacement project’.