Causer Pays Procedure Consultation

09/11/2018
Market National Electricity Market
StageFinal Report
ConvenorAEMO NEM
Initiated09/11/2018
Accepting submissions?No

Notice of Final Report and Determination – Regulation FCAS Contribution Factor Procedure

National Electricity Rules Rule 8.9

Date of Notice: 9 November 2018

This notice informs all Registered Participants and interested parties (Consulted Persons) that AEMO has concluded consultation on amendments to the Causer Pays Procedure – renamed to the Regulation FCAS Contribution Factor Procedure. The final report and determination is provided below, along with all submissions received during the two stages of consultation.

This consultation was conducted under clause 3.15.6A(m) of the National Electricity Rules (NER), in accordance with the Rules consultation requirements detailed in rule 8.9 of the NER.


 Final Report

Second Stage Consultation Participant Responses

Draft Report and Procedure

Downloads

First Stage Consultation Participant Responses