Consultation timeline
-
Consultation open1 August 2023
-
Submissions close15 August 2023
-
Final determination published31 August 2023
-
Guidelines become effective31 August 2023
Overview
AEMO has made a final determination to make minor or administrative changes to the Inter-Network Test Guidelines under the National Electricity Rules (NER) 5.7.7(k), in accordance with the minor rules consultation procedure under NER 8.9.4.
The final amended Inter-Network Test Guidelines is published in marked-up form, and will take effect on 31 August 2023.
AEMO received no comments during the consultation, and has made further minor clarifications for accuracy and consistency in describing the role of the Executive Joint Planning Committee. A mark-up of the changes between the draft and final has also been published on AEMO’s website.
Submissions are now closed. Please send any queries about this consultation to: internetwork.testing@aemo.com.au
Final Documents
-
31/08/2023
Final Inter-Network Test Guidelines v2.2 Clean
654.81 KB -
31/08/2023
Final Inter-Network Test Guidelines v2.2 All Changes Marked
669.54 KB -
31/08/2023
Final Inter-Network Test Guidelines v2.2 Draft to Final Change Marked
663.29 KB -
31/08/2023
Notice of determination on minor rules consultation procedure
137.05 KB