AEMO has made a final determination to make minor amendment changes to:
- Consolidate four documents in preparation for the IESS Rule Change on 2 June 2024
- Amend the CATS Procedure and the WIGS Procedure, based on internal review and participant feedback
AEMO has made the Changes under clause 7.16.7 of the National Electricity Rules (“NER”), in accordance with the minor rules consultation procedure under NER 8.9.4.
Participant submissions to the first stage of consultation
Summary of Change Proposals Procedure | Type of Change | Proposed Effective Date | Change Proposal |
---|---|---|---|
MSATS Procedures - CATS v5.71 Change marked | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
MSATS Procedures - CATS v5.71 | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
MSATS Procedures - WIGS v5.71 Change Marked | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
MSATS Procedures - WIGS v5.71 | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
Retail Electricity Market Procedures – Glossary and Framework v4.2 Change marked | Amendment | 02 June 2024 | Consolidation |
Retail Electricity Market Procedures – Glossary and Framework v4.2 | Amendment | 02 June 2024 | Consolidation |
Standing Data for MSATS v5.71 Change marked | Amendment | 02 June 2024 | Consolidation |
Standing Data for MSATS v5.71 | Amendment | 02 June 2024 | Consolidation |
AEMO is conducting a consultation on a minor amendment proposal to:
- Consolidate four documents in preparation for the IESS Rule Change on 2 June 2024
- Amend the CATS Procedure and the WIGS Procedure, based on internal review and participant feedback.
The Procedures:
- Are published with this Notice as change marked to indicate Changes to the effective date. AEMO is not consulting on the other changes which are change marked. AEMO has already consulted on these other changes, as reflected in the Final Report. These other changes are change marked for information purposes only
AEMO proposes to make the Changes under clause 7.16.7 of the National Electricity Rules (“NER”), in accordance with the minor rules consultation procedure under NER 8.9.4.
Submissions on the Minor Amendment Proposal should be forwarded to AEMO by 5.00 pm (Melbourne time) on Friday 17 May 2024.
Submissions must be made using the response template linked below and sent to NEM.Retailprocedureconsultations@aemo.com.au
Summary of Change Proposals Procedure | Type of Change | Proposed Effective Date | Change Proposal |
---|---|---|---|
MSATS Procedures - CATS v5.71 Change marked | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
MSATS Procedures - WIGS v5.71 Change Marked | Amendment | 02 June 2024 | Consolidation/Minor Amendment |
Retail Electricity Market Procedures – Glossary and Framework v4.2 Change marked | Amendment | 02 June 2024 | Consolidation |
Standing Data for MSATS v5.71 Change marked | Amendment | 02 June 2024 | Consolidation |